on ‎2017 Aug 31 7:06 AM
Hi All,
I have few materials in R/3 for which there are PVs which are not getting CIFed to APO.
I tried CIFing manually by running RIMODINI then CFM2.
BoM master data and routings are correct.
Any other checks i should do??
Thanks,
Ramesh
Request clarification before answering.
Did you first created an integration model in CFM1 with right filter criteria (I hope the criteria is selecting these materials, you can check in CFM1 itself)? What do you expect; ppm or pds?
Also ensure that these materials are not in another IM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ramesh,
Please note that this questions was under the wrong tag.
SAP Contact Center is for telephony.
SCM APO Masterdata (MD) seems to be the right place, so I moved your question to that tag.
Best regards,
Lloyd
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 16 | |
| 5 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.