Hi Experts,

The following business requirement is exposed: Purchase Requisitions documents generation without any reference from a supplier and using the "Planned Delivery Time in Days" value for lead-time defined in the Location Materials master. Planning using a supplier source is not a requirement in this business model.

We have defined materials of type "raw material" required by a finished product structure (PDS), these has no stock and no source of supply, and has defined in the Location Materials master a Procurement = External (F) and "Planned Delivery Time" value in days. We tried to execute "Order-Based Planning: Constrained Forecast Run" operator, but the optimization doesn't determine Planned Orders and Purchase Requisitions, and reports a Gating Factors of "kind Dummy Order - No source of supply found".

On the other hand, when a source of supply exists (creating Purchase Info Record in ECC and transfer to IBP R&S order-based using SDI as transportation lane), then the optimization ends correctly and generates the planned orders and purchase requisition without gating factors.

So, it is mandatory to define a source of supply with transportation lane to a supplier for each raw material, to get a successful optimization? In SAP APO this is not necessary, given that it was possible to generate a "dummy" purchase requisition without an reference supplier, using the delivery time of the material master data.

Best regards,

Accepted Solutions (1)

Accepted Solutions (1)

ankpatel
Contributor
0 Likes

Yes, that is one of the ways to generate dummy Preq. Create Dummy Lane and run confirmation run, it should give you results.

Answers (1)

Answers (1)

ankpatel
Contributor
0 Likes

Hi Dagoberto

As of now, it is not possible in R&S to generate Dummy Preq without having a source of supply.

Regards

Ankur

Former Member
0 Likes

Thanks Ankur,

I think that a way to model this is using a "dummy" supplier to create info records in ECC, or do you see another more efficient way to model this?

Best regards,