Hi,
I am trying to use the FFF class with embedded PPDS. The materials are marked with advanced planning. I have created the mpn-mrp sets. This is working correctly on the S4 side but not working when the materials are made PPDS relevant.
Is there a different master data maintenance or do we need to CIF the FFF class in the PPDS layer to make this work?
Regards,
Ninad
Request clarification before answering.
Hello,
You can only transfer simple discontinuation data via CIF. You will have to maintain the discontinuation FFF class in /INCMD/UI.
Regards,
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your response. I have maintained the FFF class in /incmd/ui but still this does not seem to work. My leading material is X and the FFF class has 2 materials X and Y. FERT material is A, which has material X has the component. I have enough stock of material Y to cover the dependent demand coming from material A but still system creates a preq for material X. Is the FFF class really supported with PP/DS or my understanding of how FFF class works is not correct.
Regards,
Ninad
Hello
I am afraid FFF class is not supported in PPDS.
Product Interchangeability in PP/DS
Also refer KBA
1405636 - Implementation recommendations for APO 7.0 MD, INT, INC
Regards,
Abhishek Rai
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.