Process Order Pegged to wrong Dependent Demand

SAPSupport
Employee
Employee
0 Kudos
461

Even when I have stock, my PrcOrd has a dynamic pegging relationship to the DepDemand of another PrcOrd.

I want the pegging relationship between dependent demand and stock.


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee
0 Kudos

Hello,

Please note that the dynamic pegging is determined based on the master data settings.

More information can be found on SAP Help:

https://help.sap.com/docs/SAP_SUPPLY_CHAIN_MANAGEMENT/5632d7cbffa04b21be22106e9a212038/02e4ab50135e0...

https://help.sap.com/docs/SAP_SUPPLY_CHAIN_MANAGEMENT/5632d7cbffa04b21be22106e9a212038/862ac95360267...


There it is said the following:

"The system must peg requirements elements and receipt elements, in accordance with the pegging strategy defined by the user for the product (for example, it must first use the earliest receipts in the pegging interval)"


So, in case there is firmed receipt close to the requirement date and time, and you are using Pegging Strategy "Use timely receipts", it is expected that the receipt closer to the requirement will be pegged.

In addition, in the following SAP help, there is more explanation about which stocks are considered by pegging:

https://help.sap.com/docs/SAP_SUPPLY_CHAIN_MANAGEMENT/5632d7cbffa04b21be22106e9a212038/d22fc95360267...

The stocks are only relevant for pegging if you have configured this in the location product master on the Demand tab page under Available Stocks.