on ‎2019 Sep 10 7:56 PM
HI,
Our planning team requested an enhancement in availability check process in which some specific material types should not consider availability check during process order release.
We've checked that is possible to implement rules by order types and plant (tcode OPJK) and do not use availability check. However, it is not possible to implement these rules by the combination: material type and material group.
It will be necessary a ABAP development and we found just a enhancement spot in function module CO_ZA_AVAILABILITY_CHK_ORDER.
Is there any other solution that allows us to include these rules instead of using an enhancement spot?
Application Component: PP-PI-POR
Request clarification before answering.
Hello,
For these component materials you can set the availability check KP No check in MRP 3 view.
Or other check groups that deactivate the ATP in OVZ2.
Material whose material master has a checking group entered in which this indicator is set (checking group KP is delivered this way in the R/3 standard system) is never included in a material availability check.
Please refer SAP consultiing note 321803 - Explanatory notes on the ATP Customizing
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 8 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.