Prevent goods receipt for material in EWM

0 Likes
2,448

There are some materials in stock which are must be stopped to be procured. We would like to prevent goods receipt for this material in EWM system since any restrictions in ERP causes queues in Smq2 and don't prevent goods receipt in EWM. Is there any possibility to prevent goods receipt in EWM for particular materials ?

Accepted Solutions (0)

Answers (5)

Answers (5)

mayurs819
Explorer
0 Likes

You can use the process block profile to restrict the movements in and out of the warehouse.

This indicator can be maintained at product master and configured to restrict the relevant processes (GR-INT-GI-PI) with control on error messages as well (Warning/error)

This indicator is available in the warehouse product master warehouse views.

JuergenPitz
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi,

what you want to do is called "Goods receipt control" here: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/9832125c23154a179bfa1784cdc9577a/85705258fd989144e10....

It of course starts with blocking the goods for procurement, but you can also block the GR. This works for embedded EWM (as in the link), but also for decentral EWM.

Brgds

Juergen

---

All the above is no official SAP statement.

Want to learn EWM?

Check for EWM courses: https://training.sap.com/trainingpath/Applications-Extended+Warehouse+Management-EWM+in+S4HANA

Get a SAP Learning Hub Subscription: https://training.sap.com/learninghub

And it is EWM. NOT eWM - Duh!

And if your question includes the word "transfer order" - do NOT tag the question with Extended Warehouse Management!

Daniil
Active Contributor
0 Likes

Hi,

Just as a simple idea, you can create new process indicator and determine special warehouse process type, to have no GR bin in the delivery. One would need to maintain delivery manually to post GR.

Second option could be to use special availability group (in the process type) which has no proper mapping to avoid GR, not sure if it would work for delivery.

Andreas_Mergler
Contributor
0 Likes

Hi,

I guess you need to describe your business case a little more in detail.

From the posts I have learned that you want to do "internal movements" - I assume that is internal in EWM. So that stock must have been received in EWM earlier, i.e. before you decide to GR. Are these GRs against a purchase or production order (or the inbound deliveries from them)?

You wrote that materials "must be stopped to be procured" - that can be achieved using material status (in ERP). If the status is set accordingly you cannot create purchase orders ... an no inbound orders for EWM either.

BR Andreas

ankurch
Active Contributor
0 Likes

Hello There,

Just maintain the material master record for warehouse management views in MM02, so that user shouldn't be able to post the GR due to insufficient info in Material master record.

Thanks,

0 Likes

No it doesn't help since it blocks internal movements also. Moreover, we need to prevent GR in EWM since otherwise EWM allows to post GR and errors would stuck on SMQ2

ankurch
Active Contributor
0 Likes

if you want to block only procurement then do it through MM06.