Hello experts,

We're trying to implement two PPF actions. The actions themselves are ready to be used and have worked properly in other systems. The two actions are intended to transmit certain data to third-party-programs when certain statuses are set in the freight order.

Our requirement is to set up the trigger for these actions, which I believe to be the Schedule Conditions. Is there a simple way to configure and assign a Schedule Condition (or other way to trigger it) to these actions? As for now, the assigned Schedule Condition is the standard /BOFU/EVAL_SCHEDULE_CONDITION.

An example of what we would like to do is: If the status Lifecycle is (manually) set to "completed" (05) then the condition is fulfilled and the action is triggered.

Regards,

Tim

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member809312
Contributor
0 Kudos

Hi Tim,

You might need a development for that, using a Class asigned to the PPF action to call the status change on the FO.