on ‎2020 Sep 15 7:45 PM
Hello expert,
I am new to the SAP PPDS and need your help on below S4PPDS(v1909) production planning issue.
I have created FG and a component and CIFed to PPDS with resources and PDS. In RRP3, I have created the 2 Fcst Requriment for the same date and execute the SAP_PP_002 heuristic. It creates 2 planned orders at the FG level but 3 dependent requirements at the components level.
I was expecting 2 dependent requirements at the components level.
Kindly let me know is any more settings required to get the actual result.
Thanks
Srikant
Request clarification before answering.
Hello Brahmankar,
Thank you for your reply.
There is only one component in the FG material.
And If I only run the product heuristics(before saving the data), It creates 2 planned orders at the FG level and 2 dependent requirements at the component level. once I saved the data in the RRP3, 3 dependent requirements are created at the component level.

Components

Please let me know if you need any additional information.
Thanks
Srikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
How many components are there in your BOM of FG materials?
2 Fcst Requirements for the same date then it should be for two different FGs. Please check these FG BOM and PDS for components.
Please share the screen shot of product view for dependent requirements.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.