PPDS Planned Order Start, End dates should be equal

former_member941333
Discoverer
0 Kudos

Hi

When I am running Std Lot 3 Horizon Heuristics, the Mid Term, Long term Planned orders have huge gap between Start and end dates. Is there a way, we can see start date matching with the end date ? I have 0 In house Prodn time, 0 GR time defined.

I think we need to ignore the PDS lookup for this so the time defined in the routing is not considered. But for Short term horizon, we want to see the correct start, end dates/times.

Is there a way to achieve this ? Appreciate for any pointers.

Thanks

Narendra