Hi all

Is there any way to prevent the system to schedule an order to start before weekend and finish after the weekend?


We cannot stop or keep the order during the weekend so the order should finishes before weekend or start after weekend.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

During the scheduling in the PPDS, orders are created over a weekend and thus at a non-working time

You need to use a strategy for scheduling which does not allows the scheduling of activities at non-working times.

Alsoin Detailed Scheduling Planning Board (/SAPAPO/CDPS0) check if the setting "Non-Working Times" is checked in DS strategy

For more details please refer SAP consulting note 397989 - PP/DS: Scheduling (Documentation)

Best Regards,

R.Brahmankar

carlos_perez8
Participant
0 Kudos

Thanks, but what I need is to start and finish the order before the weekend or after, I don`t want to schedule in non working time and the order to be stopped

rupesh_brahmankar
Active Contributor
0 Kudos

Hello,

It means you need a order which should get scheduled within a week, in that case you can use the max lot size as per the capacity of week with planning calendar.

Best Regards,