on 2020 Jun 09 2:17 PM
Hi all
Is there any way to prevent the system to schedule an order to start before weekend and finish after the weekend?
We cannot stop or keep the order during the weekend so the order should finishes before weekend or start after weekend.
Request clarification before answering.
Hello,
During the scheduling in the PPDS, orders are created over a weekend and thus at a non-working time
You need to use a strategy for scheduling which does not allows the scheduling of activities at non-working times.
Alsoin Detailed Scheduling Planning Board (/SAPAPO/CDPS0) check if the setting "Non-Working Times" is checked in DS strategy
For more details please refer SAP consulting note 397989 - PP/DS: Scheduling (Documentation)
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.