PP/DS purchase order

itsgzc
Explorer
0 Likes
669

Hi everyone,

I've a problem about purchasing order maturity date. Let me explain. I am opening a purchase order for 3 different semi-products under the semi-product that I produced. There is no problem when I scan that purchase orders in Sapapo/rrp3 but their available time 10 august. When I checked sapapo/cdps0, the system makes planning on August 2nd for this semi-finished product that I produce. Actually It needs to plan for 10 august or later because 3rd level semi-products out of stock. How can I fix it and get the system to alert me?