Hello Friends:
please I need your help because, I am using PP/DS: SAPAPO/CDPSC0 - Detailed sheduling planning board. My case is when I move an operation where there is slot in its resource, its before operation is overlaping, so Is there a way to prevent this, maybe alerts?
Request clarification before answering.
Hi,
What is the DS strategy on your scheduling board? Can you change it to "insert operation" when you are trying to move an operation to fill gap.
Regards
AK