Hi,
I have this problem. I have several resources (5) to schedule in PP/DS and I have process orders to manage.
If I try to move order from Orders chart to resource chart, with drag and drop function, order move only on the default resource. If i want to move process order on another resource i need to execute right click mouse on the order and select "Switch Source of Supply Order" then I select the new resource in list "Admissible Source of Supply". Why don't work with drag and drop function? I have several process order and end user can't change resource in this way (the request is move order from resources with drag and drop function).
Please how can i do?
Request clarification before answering.
Hi,I fixed problem using alternative resource. Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Have you maintained the other resource as alternative resource in the mode in PDS?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.