on ‎2017 Feb 02 1:00 PM
Let me explain the scenario
I have FERT materials that generate dependent demand to HALB materias from the PPMs. I run my MPS process using Heuristic "SAP_MRP_01" and also it generates unrestrict planned orders in all the levels (FERT/HALB). But due capacity restriction my bottleneck is the HALB material, so what I am expecting is to run Heuristic in FERT material to reschedulle or reduce the quantity for the FERT based in the constraint in the HALB material. So like running a Finite heuristic in FERT material that will check the availability of the HALB component.
I am thinking about Pegging heuristic, can somebody confirm whether this works?