on 2023 Jan 25 2:53 PM
Hi Expert,
In inbound delivery, i have input actual GR 24.01.2023 then expect that EWM will follow the same. after EWM completion, it has changed to current date 25.01.2023 which made posting date in material document was 25.01.2023.
is there any way to get posting date in EWM as same as actual GR date in ERP?
Please kindly advise.
Regard,
RTN
Request clarification before answering.
By default EWM will use current date as posting date.
If you need to influence the date please see note 2574109
https://userapps.support.sap.com/sap/support/knowledge/en/2574109