on 2022 Jan 20 2:56 AM
Dear Experts,
Material to Material conversion is done from ERP and a PCN delivery is created in EWM.
M1 is converted to M2.
M1 has fixed bin B1 and M2 has another fixed bin B2.
When warehouse task is created for the PCN, system determines B1 as the source as well as destination bin.
System is expected to determine destination bin = B2 as the converted material has to be placed in its fixed bin.
Kindly suggest if there is any way to overcome this system behavior.
Thanks,
Mageshwaran Sivasamy
Request clarification before answering.
Hello,
Material to material conversion means material code to code conversion using movement type 309.
Example. 100 PC of Material1 to Material2
Thanks,
Mageshwaran Sivasamy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 10 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.