on ‎2020 Jun 29 10:20 PM
Hi,
I did not understand whether should be POSC define for 2 Step Picking. There has a blog about 2 step picking and he doesn't use POSC for 2 Step picking. He determine destination storage type and storage bin in WPT. When I try to do 2 step picking without POSC, like that blog, second WT doesn't create. Materials pick from intermediate stroage type. Then I try to do via POSC. but I know in outbound processes the POSC is always determined via the warehouse order creation rule. I'm confused 😞
Here is the blog which I mentioned above: https://blogs.sap.com/2018/09/09/two-step-pick/
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi,
in two-step picking the second WT is not created automatically. It is not the same as storage control. Have you read the documentation? https://help.sap.com/viewer/9832125c23154a179bfa1784cdc9577a/1909.002/en-US/4f4c0f1befea13ade1000000...
Brgds
Juergen
---
Want to learn EWM?
Check for EWM courses @ https://training.sap.com/trainingpath/Applications-Logistics+Execution+%26+Warehouse+Management-SAP+...
Get a SAP Learning Hub Subscription: https://training.sap.com/shop/learninghub
And it is EWM. NOT eWM - Duh!
And if your question includes the word "transfer order" - do NOT tag the question with Extended Warehouse Management!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you so much. I have taken some errors because I incorrectly determined the warehouse process type. Then I changed the warehouse process type.
"...relevant material will be picked from the storage type 0070 to move the storage type 2010 with using the process type 2020 and then it will be picked from the storage type 2010 to move the storage type 9020 with using the process type 2010." quotation
First I set Determine WPT 2020. But that was wrong. I must have set 2010. When I set WPT 2010, then problem resolved.
I do first Release Withdrawal and the first WO creates. Here, materials go from main storage type to the intermediate storage area. Then I click on Release. Then the second WO creates. In the second WO, materials go from the interim storage to the Staging area.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.