Hello Experts,
what is the difference when
1. resource( Labor) Maintained as secondary resource in a recipe and
2. capacity (Labor) maintained as pooled resource in recipe ? In terms of Scheduling in APO ?
Regards
Alin
Request clarification before answering.
Hi Alin,
The secondary resource in Master Recipe will act as a suboperation in the PDS - it will be a different activity (with it's own mode) and could possibly have different duration to that of the main operation/phase. Activity relationships will be generated in the PDS between the main operation and the secondary resource.
When a secondary capacity is used, on the other hand, it will have the same duration as the main phase. In this case, a capacity requirement is added in the PDS for the secondary capacity under the main activity.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.