Today , when the approver not approve the PO within 5 days the workflow move to 1st backup.
But I don't know if it's 5 working days ,open day or based on factory calendar.

=> I would like to know how the dealine shall be counted in approval workflow, if we need to consider factory calendor here. Also if holidays are counted to count deadline?

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

fernanDoylet
Explorer
0 Kudos

Hi @regis1972 
As far as I know, those are calendar days. So yes, days off and holidays are counted.