on 2024 May 27 11:57 AM
Hello,
We have implemented EWM and with order release the PMR is created.
Can you please help me how to setup ECC so when I reschedule order or change quantity of component the PMR update is automatically send to EWM?
Thanks
Request clarification before answering.
After investigation we got the answer. For the material and order we were missing scheduling profile:
With setting to transfer the orders requirement = 2
That is why only manual execution of WM staging was sending the information to EWM.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Still not solved. Any tips?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
check out solution from SAPnote 2811153 - Manufacturing Integration: Automatic creation / update of expected goods receipt in SAP EWM.
Kr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.