Work centers in PM should be master data or configuration data? What is the best practice in case person assignment is mandatory in work center. Please explain with the perspective of PM.

Accepted Solutions (0)

Answers (1)

Answers (1)

Oscar_DC
Active Contributor
0 Kudos

In standard they are master data. Even if you could handle them as configuration data - which I don't think you can- I would argue that they should be master data.

Employees retire and crews change - that happens in my company all the time.