PM Dynamic priority

0 Likes
191

Hi,


So the company I work for has various labour constraints.

Long story short, we have missed 10 4weekly PMs on some equipment resulting in a catastrophic fail.


The 4weekly PM will have identified this growing issue. It was missed because it was a priority 3 (medium). Our medium priority completion rate is 43%. Not much we can do about that.

Our priority 1 & 2, safety and urgent, is 100%.

Can SAP identify automatically that these PMs had been missed, and change this priority from a 3 to a 2 on the following PM to be released?

I know we can change the structure in doing a 6 monthly PM as a priority 1 etc. But, for now, is the about possible??


Thanks,


Sam