Planning calender in APO changed automatically

0 Likes
826

Hello,

I don't know how but planning calender in SAP APO product master changes to previous one after overnight process.

I have tried to change 2 times, but when I change it, it is changed but when I check next day it comes to previous one.

Please help.

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Your planning calendar is changing overnight means this could happen through batch job.

There is no option to automatically generate the planning calendar periods. You can only generate periods manually in transaction /SAPAPO/CALENDAR.

Or by using report like ZZTSTRREGENERATE or ZZ_TIMESTREAMS_CALC_PERIODS

Also check the where used list for table TTSTR if you have your any Z report for time stream generation.

You can also check the report from note 1421812 which can generate all the time streams automatically in a mass way.

Best Regards,

R.Brahmankar

0 Likes

Planning calendar period is not changing, The planning calendar is changing in product master.

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

Did you check the product master change log /SAPAPO/PROD_CD_READ - Display Change Documents?

As this field do not transfer from CIF, so do you have any enhancement to update in product master ?

Best Regards,

R.Brahmankar