Planning calender for making periodic deliveries for raw materials

kailas_elavelil
Explorer
0 Kudos
169

Dear all,

I am setting the periodic delivery of raw materials :- first week wednesday in every month. What I did is

1. changing the lot size procedure to a custom procedure. It has priod lot sizing procedure(P) , indicator as as in PPC calender (K) and scheduling period start = availability date    ( see the screenshot) 

2. created a new calender with 'monthly ' as calculation rule and with periods as in screenshots

my questions are 

a. is my period creation wrong ? If so what should i change?

b. have I missed any other settings in material master ? My MRP type is PD and I assigned the planning calender and Lot sizing procedure to the material master already. 

c. What is the steps if I need a period delivery and the MRP run based on a planning calender?

Thank you. Please feel free to ask questions if I am not clear with any information.