on 2024 Jun 27 9:09 AM
Dear all,
I am setting the periodic delivery of raw materials :- first week wednesday in every month. What I did is
1. changing the lot size procedure to a custom procedure. It has priod lot sizing procedure(P) , indicator as as in PPC calender (K) and scheduling period start = availability date ( see the screenshot)
2. created a new calender with 'monthly ' as calculation rule and with periods as in screenshots
my questions are
a. is my period creation wrong ? If so what should i change?
b. have I missed any other settings in material master ? My MRP type is PD and I assigned the planning calender and Lot sizing procedure to the material master already.
c. What is the steps if I need a period delivery and the MRP run based on a planning calender?
Thank you. Please feel free to ask questions if I am not clear with any information.
Best regards,
Kailas
Request clarification before answering.
User | Count |
---|---|
8 | |
5 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.