Hi dear colleagues,

I'm facing every day with firming the planned orders. We receiving the orders by EDI and i usually use for firming mf50, but few days I'm thinking about how to easily firm all planned orders till end of the forecast with minimal steps.

My question: Is there any way to import them from excell file for example or other mass transaction to schedule? I'm searching for more efficient transaction for mass objectives.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

The firming logic is determined by the repetitive manufacturing profile in Customizing OSP2. The following firming options exist:

1. 0 = Not firmed

2. 1 = Always firm

3. 2 = Firm within planning time fence

All newly created and all changed planned orders are firmed according to the REM profile in MF50.

So fro your REM profile define Firm within planning time fence and in material mater MRP 2 view maintain the planning time face to get the order firming until planning time fence.

Or with transaction MD19 you can firm planned orders in mass.

Also refer

Mass Changes of Planned Orders (Action Control)

Best Regards,

R.Brahmankar