on 2022 Oct 13 9:22 AM
We have a problem like user has created a firmed planned order,it has two components.There is a process chain that generates the planned order for them in the weekend. But in the next day,that planned orders for the components is getting deleted.
We did not find any job running in APO end which can delete that.Can the MRP run delete the planned orders for that component products and we saw opening period in PPDS tab is set as 1 day.
Request clarification before answering.