Why system set basic finish date on day when work-center is down for maintenance?
In my case, system has scheduled planned order basic finish date to July 27th and doing backward scheduling. while work-center is down (0% capacity) from July 24 to July 30th.
This planned order supposed to run for 3.5 days considering system putting start date to July 20th which is correct, but it shouldn't kept finish date to 14th, because that and equal distribution key calc MD04 showing planned order on all days from July 20th to July 27th.
Refer below screen for more understanding. Reply appreciated.
Request clarification before answering.
Hello
The basic finish date is generally calculated by MRP and it will try to match the requirement date for which the planned order was generated. In the basic date calculation, the plant factory calendar is considered instead of the work center calendar.
The work center factory calendar is used for the calculation of the production dates and the order finish date is not adjusted with the productive dates.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Cateno for explanation. When I convert planned order to production order then system/ MRP does consider work-center downtime and do not schedule order during downtime. Is it system standard behavior? Can we manage planned order to behave same as production order?
Erir.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.