on 2024 Jun 18 10:14 AM
Hi Guys,
The planned order is getting the production version but, despite I perform the scheduling, the system do not determine any work center at the detailded scheduling tab.
I performed the regenerative MRP as well.
thank you so much guys.
But, when I do the conversion to production order, the system gets and show correctly the work centers.
Request clarification before answering.
Hi @Oscar2,
my best guess is that you did not provide standard values in the routing operations. If you have set-up master data in your SAP system which is working as expected I suggest to compare routing and work center data.
Kind regards
Franziska