Planned order Days calculation in APO

Former Member
2,343

Hi All,

Planned order availability dates are misaligned between APO/ECC for material. APO consider Saturday and sunday.

I checked Location calendar as well as resource calendar. its 5 days week in APO.

Please guide where system consider 7 days for calculating avlb date.

View Entire Topic
former_member197994
Active Contributor

Hi Suren,

A handling resource should be 7X24 available. Is there GR processing activity in the order?

Best regards,

Tiemin