Hi All,
Planned order availability dates are misaligned between APO/ECC for material. APO consider Saturday and sunday.
I checked Location calendar as well as resource calendar. its 5 days week in APO.
Please guide where system consider 7 days for calculating avlb date.
Request clarification before answering.
Hi Suren,
A handling resource should be 7X24 available. Is there GR processing activity in the order?
Best regards,
Tiemin