This is a scenario
there is a long production order 27.09.24 - 30.09.24
there is a sales order requirement date 29.09.24
because of production order is long it actually will have needed quantity for 29.09.24 but when we run MRP it still creates smaller qty planned order to actually meet demand date of sales order.
i do understand why its happening but need to know how i could avoid this additional planned order. what setting i could try change.
Request clarification before answering.
Hello
Very often this is an issue with your rescheduling check. Either production orders are not included in the rescheduling check, of this specific order is outside the rescheduling horizon.
Check this WIKI for more details about the rescheduling check:
https://help.sap.com/docs/SUPPORT_CONTENT/mrp/3138697863.html
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 7 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.