Dear Gurus,

I had a PIR on February, being consumed by withdrawal quantity.

I deleted the PIR and created a new one (MD61).

Withdrawal quantity is still displayed in MD73 but doesn't consume anymore the PIR I've just created.

Any idea why?

Thank you.

Accepted Solutions (0)

Answers (1)

Answers (1)

SteevesSegura1
Explorer

Looks like this is normal.

OSS note 812592 - MS64 berücksichtigt keine Entnahmemenge der Zielversion