on 2021 Jan 06 11:55 PM
Hello Experts,
Basic question but what would be an affect of changing the Planned delivery time in Material master during APO planning run. I understand PDT is usually used for the MRP run and when the product is externally procured but would there be any scenario that we need to consider from APO planning run perspective that this change my affect? Let me know if you have any questions to answer the doubt above.
Thanks in advance
Request clarification before answering.
| User | Count |
|---|---|
| 12 | |
| 11 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.