Hello all,

in our storage type full pallets are stored in Handling Units. For picking the system creates one single warehouse task (= 1 pallett) per warehouse order. This is defined in the warehouse order creation rule.

In RF device the forklift drivers start picking by "Selection by WO".

Requirement:

In future we want to print the warehouse orders. But if we have a large order quantity, too many documents would be printed due to many warehouse orders.

So I checked if we can change the warehouse order creation rule so that we have for example 10 warehouse tasks per warehouse order.

Then we have the following sequence.

  1. Picking HU1 from source bin LP01
  2. Picking HU2 from source bin LP01
  3. Confirming destination bin WAZO (HU1)
  4. Confirming destination bin WAZO (HU2)

But actually we want to have the following sequence.

  1. Picking HU1 from source bin LP01
  2. Confirming destination bin WAZO (HU1)
  3. Picking HU2 from source bin LP01
  4. Confirming destination bin WAZO (HU2)

Is it possible to change the picking sequence as described?

Using exception code NEXT would not be an option for us.

Thank you in advance!

Best regards,
Julian