on ‎2019 Jun 07 4:21 AM
Hello Experts,
This issue is related to Synch between APO and ECC system.In this case they are not in synch.The completed deliveries in ECC(Viz. PGI and invoicing already completed) are still seen in rrp3 (product view)screen as In-Transits.
Is there any way we can avoid this from happening meaning once the delivery is goods issued it should be knocked off from RRP3 screen and Qty should get reduced
Request clarification before answering.