on 2018 Dec 20 4:07 PM
Dear All,
I would like to share with you this requirement in the IBP Response & Supply (Order-Based Planning area).
The requirement is:
Do you have any idea?
Is it may possible to have a priority equal to “null” or “ – 1,000” for this “Manual PDS”?
Thank you for any kind of support.
Regards,
Vivek
Request clarification before answering.
Hi Vivek,
you can achieve this by maintaining a low SOS Priority and adjusted production key figure value of 0.
With that the confirmation run will not use this PDS.
Planners can maintain adjusted production key figures -> PDS will be used by the next confirmation run.
I hope that is supports your requirement.
thanks and regards
Michael Mack
IBP Product Management
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 14 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.