on ‎2025 Feb 18 8:15 AM
Hi Team,
We have /scheduleOrders API under Order Schedules Package for DMC system to Retrieves all operations for a given order and schedules it to the corresponding resource and work center on the shop floor for a specified date range.
I have trying to use this service but i when i am trying to schedule one order, it is working fine but with the another order (copy of same order), i am getting error as "There is a scheduling error with the order."
I am passing the Order Planned Start Date and Completion Date only for scheduling.
Anybody has any idea on this?
Thanks,
Nikhil Gupta
Request clarification before answering.