Order not scheduling over downtime

SAPSupport
Employee
Employee
0 Kudos
369


Hi Team,

Order not scheduling over downtime, it is scheduling before or after downtime.

Regards


------------------------------------------------------------------------------------------------------------------------------------------------
Learn more about the SAP Support user and program here.

Accepted Solutions (1)

Accepted Solutions (1)

SAPSupport
Employee
Employee
0 Kudos

Hello,

As mentioned in the following SAP help, the order activities cannot be interrupted by downtimes. This means the activities always come completely before or after a downtime.

If you move an activity in the planning board over a downtime, then the activity "jumps" behind the downtime.

https://help.sap.com/docs/SAP_SUPPLY_CHAIN_MANAGEMENT/5632d7cbffa04b21be22106e9a212038/9b47c95360267...

In this help link there is a BADI implementation to change that, however, the custom logic is a responsibility of the customer and we cannot analyze it.

In case of questions regarding the BAdI, please ask our community.

Best regards

Yasmin

andy_yeri
Contributor
0 Kudos

Can this not be done using the SHORT BREAK = 99999999 value on the PDS_MAINT transaction? I know it works to schedule the orders spanning over the break times, does it not do the same for DOWNTIMES?