on 2022 Nov 01 12:53 PM
Hi,
IN POSC Inbound process.
I am following 3steps
Step1: IB01 - Unloading
Step2: IB02 - Deconsolidation
Step3: VAS - VAS
Step3: IB03 - Put away
Getting error while completing Process step for HU in Deconsolidation Work center.
Error - Only HUs with storage process can be completed
So, please suggest me if there is any setup has to be done.
Thanks & Regards
Revanthkumar
Request clarification before answering.
Hi, check if you process is determined. It should be in the HU (detail 1)
I do not see product wts on your screenshot, it does not look as a normal DECO process for me.
BR,
Daniil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.