OBP Planning infinite Run

OliverA41
Active Participant
881

Hello,

in OBP I have a finite Heurisitc and Optimizer. But how can I change the quantitiy of the production if I want plan inifite.

Give it a key figure, wich I can overwrite the result of the Heurisitc run and furthermore der result in s4 (e.g. Plauf is my overwrite value )

Regards

Oliver

Accepted Solutions (1)

Accepted Solutions (1)

former_member654033
Contributor
0 Kudos

Hi,

Using settings in planning run profile you can run the OBP finite heuristic with infinite capacity.

Answers (4)

Answers (4)

OliverA41
Active Participant
0 Kudos

Hi Girish,

thanks for the response.

this is working perfect.

We have an further question about quatas and ratios.

Perhaps you can help me again

https://answers.sap.com/questions/13281393/order-based-planning-quotas-for-multiple-plants.html

Thanks in advance

Oliver

piyush_parekh
Active Contributor
0 Kudos

Hi Oliver,

You can also enable flexible planning start and run heuristic with planning start date in past. This makes priority heuristic run in infinite mode. Refer below webinar by SAP for more details.

https://d.dam.sap.com/a/vVhnoBN/IBP_OBP_Optimizer_Nov2020_Webinar.pdf

Regards,

Piyush

OliverA41
Active Participant
0 Kudos

Hi Lingaiah,

you are right.

sometimes I have to plan infinit. That means, that for a ressource I need 110% capacity.

If I plan this with the infinit heuristic, I get not relocation orders . So how can I plan ith infinit heurisitc and than with the deployment run in order based planning that I have a the end in the s4 system the relocation order.

thanks in advance

Oliver

lingaiahvanam
SAP Champion
SAP Champion
0 Kudos

Hi,

SAP IBP OBP supports planning algorithm "Finite Heuristic" and "Optimizer" to generate the optimal supply plan.

You can run time series supply heuristic to generate infinite plan.

Best Regards,

Lingaiah