on ‎2022 Jul 22 7:05 PM
Hi Team
We are not able to schedule orders in DS Planning Board ( /SAPAPO/CDPS0 ). Even with manual drag and drop it is not working.
Most of the deallocated orders can not be moved. Drag and try to move it, you will get the error.
The error in the logs is:
"No valid modes available for activity
Message no. /SAPAPO/DM_SCHEDFAIL013"
Request clarification before answering.
Hello,
Usually, this error message occurs when there are other activities linked to the operation we are trying to reschedule (in your case it is operation 0020). This is, the operation you are trying to schedule has internal relationships to other operations.
Therefore, when changing the scheduled date and time of operation 0020, the system tries to change the date/time of the related operation.
Operation 0020 has a relationship end-start with operation 0030. The issue is: the related operation 0030 was not selected to be displayed in the DS Planning Board. Neither its resource.
The rescheduling cannot be completed due to this restriction.
Therefore, we have some options to resolve this issue:
1) Display all resources from the order in the DS Planning Board
OR
2) Change the Propagation Range to consider all resources, even those not selected to be displayed in Planning Board (e.g. use prop range SAPALL)
OR
3) Change the Strategy Settings to do not consider the Order-Internal Relationships
More information is available in the note below:
2244236 - Scheduling error No valid modes available for activity in the DSPB
Best regards
Yasmin
SAP Support
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 8 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.