on 2017 May 25 11:26 AM
Hello All,
i checked below Actions
CIF Integrations Models Activated for below all.
Plant
Resource
Material
PDS
Process Ord
Distribution Def are maintained(031)
what could be the reason to not to covert
kindly help...
Request clarification before answering.
Hi,
Can you check the conversion rule used for converting Planned Order to Prod Order in customizing.
SPRO--> Advance Planning and Optimization --> Supply Chain Planning --> Production Planning and Detailed scheduling (PP/DS) --> Global Settings -> Maintain global parameters and defaults
Check the conversion rule in the tab 'Execute' and look it up in the path below.
SPRO--> Advance Planning and Optimization --> Supply Chain Planning --> Production Planning and Detailed scheduling (PP/DS) --> Transfer to Execution -> Define conversion rules
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 6 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.