No STR for OBP planning Run in Infinite mode

sourojit_pal
Participant
0 Kudos
231

Dear Team,As per one of the requirements in one of our project, we are trying to execute Supply Planning Run in OBP in Infinite mode. To achieve this we have already turned of all the necessary constraints under switchable constraint section in the Planning run profile.. Only production Freeze horizon is turned on as that needs to be considered as per requirement.

The expectation is that the STRs from WH to Plant should get generated but Plant should show negative projection as planned orders should not get created.

What we observe is that the system is not generating any STR to Plant during the frozen horizon.

Did anyone in the forum already face this type of issue? Is there any way to overcome this problem??

We have already switch off Capacity Constraint and scheduled the run from past as per the the SAP Document Page 11.

Regards,

Sourojit

Accepted Solutions (0)

Answers (1)

Answers (1)

girish_nitie
Participant
0 Kudos

Hi Sourijit,

Not possible with finite heuristic + freeze horizon..

If you limited receipts in freeze horizon then unconstraint STR won't be created as its finite planning heuristic.

Thanks

Girish