on 2022 Dec 27 5:55 AM
Hello Everyone,
For one of our client we have gone live in November with only PP functionality, Detailed scheduling was descoped due to the dynamic changing of No. of individual capacity which we were not able to meet the customer requirement.
Customer requirement was to maintain the No. of individual capacities at Product(Finished good) level & Time Based ( Will be varying day to day) for atleast 1 week.
Can you please suggest whether the above requirement can be fulfilled in SAP.
Thanks in Advance
Product
Resource
No. of individual Capacities
Day 1
Day2
Day3
Day4
Day5
Day6
Day7
W1
W2
W3
FG1
Resource1
3
2
6
4
8
10
8
5
5
5
FG2
Resource1
4
4
1
4
6
14
6
5
5
5
FG3
Resource1
5
3
3
4
7
9
7
5
5
5
Request clarification before answering.
User | Count |
---|---|
9 | |
4 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 |