cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

No dependent demand for phantom with planning strategy 59

Former Member
0 Likes
843

Hi Gurus,

Need your help with this scenario.

BOM structure

BOM Level            

         0                         Header material  (KMAT)                                             A               MRP type (PD)           

         1                         Phantom material   (HALB)                                         P              LRP type (X0)                Planning strategy  59

         2                         Component of header material  (HALB)                      C1

    

Dependent demand for phantom material is not consuming the phantom assembly forecast. Expectation is that a planned order for material A will create a demand for the phantom material which will consume the forecast. We can see the dependent demand generated for the phantom in ECC but not in APO. Because dependent demand is missing in APO no forecast consumption at the phantom assembly level takes place. I would see dependent demand at component level for the planned order of material A but why we cannot see dependent demand for phantom.

Configuration values are seamlessly flowing to planned order for material A in APO.

All IMs are in place. Queue is clear.

Can you please advise are there any specific setting in APO that I need to check in order to see dependent demand for the phantom.

Thanks in advance,

Asim

Accepted Solutions (1)

Accepted Solutions (1)

Abhishek_Kunchala
Active Participant
0 Likes

Hi Asim,

Can you check the PDS of the Finished Product in APO and validate that you see the expected structure with phantom assembly indicator.

Regards

AK

Former Member
0 Likes

Thanks Abhishek for your reply. I can see the expected structure for the phantom.

Abhishek_Kunchala
Active Participant
0 Likes

Asim,

The Dependent demand for phantom assembly is in ECC but not in APO which means that the Dependent demand may not not CIF'd to APO. You can start with CFM5 in ECC by choosing the phantom material and all transaction data and then perform a CIF Reconciliation in APO. Can you look up the phantom material in RRP3 view at the location where the PDS exists. Another approach would be to look up the pegging relationship for a Planned Order of Material A and see if has components along with phantom material.

Regards

AK

Answers (1)

Answers (1)

tiago_furlanetto
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Asim,

In PP/DS, a dependent demands are not created for the phantom product itself in standard, it is not expected that planning activities will take place for the phantom. Rather, only for the components are dependent demands generated.

This is described in SAP Help below:

Phantom Assembly - Integrated Product and Process Engineering (iPPE) - SAP Library

"Phantom assemblies do not trigger any dependent requirements. Only the components of the phantom assembly trigger dependent requirements."

Regards,

Tiago