on ā2025 Nov 11 10:24 AM
Hello,
Retest Date Finished Product is calculating based on last good receipt is possible to make system to calculate it based on manufacturing date
here is example :-
Mfg. Date: Sep -2025
Retest Date: Aug-2029.
In SAP:
Mfg. Date: 21.09.2025
Next inspection date should be 20.09.2029
But the system is considering the next inspection date as 09.11.2029 from date of last goods receipt i.,e 10.11.2025