debugger.jpghi experts,

today, I have the task to integrate a process in TM which is normally not integrated. A purchase order generated by a third party sales order. The product will be delivered directly from the vendor, but the transport is still organized by the customer“s transport team. I have created the integration customizing for the purchase order and run report report /SCMTMS/CHK_DOC_INT_TM_INTEGR in se38. as a result, I get attached picture. goods-receipt-indicator.jpg.

The debugger stops in the exit that allows changing the locations (/SCMTMS/IF_LOGINT_CHG_TRQ_MM) I have coded a loop over the header and item data as attached. But, I cannot identify which indicator is the goods receipt indicator and the item has a product and not a service product. has someone faced the same issue or can help me?

Thanking you in advance

Petra

Accepted Solutions (1)

Accepted Solutions (1)

petra_just
Active Participant

hi,

just to update my thread: The system checks in standard coding AFTER the exit that there is a goods receipt flag set in the purchase order. Apparently, POs that are not goods receipt relevant cannot generate a freight unit (see attached debugger). This issue is related to S/4 Hana 2020 embedded TM .

So, I have contacted the MM team to see if they can make the PO goods receipt relevant without posting a real goods receipt.debugging-po-check.jpg