Need to change description of PPM in mass

former_member332160
Participant
0 Likes
205

Hello Expert,

There is need to change the description of too many PPM. is there any way by which we can change the description of multiple PPM  in mass.

looking for help:)

Thanks,

Jitendra

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

In R/3 change Routing Group Counter Description, in mass you can do that with CEWB then CIF it across it will update Description of PPM.

In APO you can also do the  mass changes for PPM through MASSD   for component /SAPAPO/PPM_MASS_PLAN Plan Description.

However CIF will overwrite it. So it better do the changes in R/3.