on ā2016 Feb 03 7:21 AM
Hello Expert,
There is need to change the description of too many PPM. is there any way by which we can change the description of multiple PPM in mass.
looking for help:)
Thanks,
Jitendra
Request clarification before answering.
Hello,
In R/3 change Routing Group Counter Description, in mass you can do that with CEWB then CIF it across it will update Description of PPM.
In APO you can also do the mass changes for PPM through MASSD for component /SAPAPO/PPM_MASS_PLAN Plan Description.
However CIF will overwrite it. So it better do the changes in R/3.
Best Regards,
R.Brahmankar