on 2015 Dec 22 9:14 AM
Hi all
I want to set up a multi mix resource to have time and capacity in T for example.
In the Time-Cont capacity tab I enter MASS and the capacity 20T.
The systeme is multipling 20 times 24 hours a day to get 480 hours available. I want to limit to 20 T a day.
I the routing in ecc is T per H.
What I am misising?
Thanks in advance
Request clarification before answering.
In SNP bucket capacity tab of resource master you should choose "maintain" (instead of "from continuous") and then maintain the capacity in different units in the fields that will open up.