Dear team
We want to run MRP for 6 months and we do not want MRP to consider batches which are going to expire in 6 months in future.
BR
Ramesh Kumar
Request clarification before answering.
Hello @rammeshokumar
SAP standard MRP works on material number level. It doesn't go down to batch level. Thus, your requirement can't be implement in standard. I guess you could use MRP BAdIs and try to manipulate stock levels during MRP planning. It might work, however I don't think it's the way to go.
First, do you really want to remove all the batches expiring in 6 months from MRP planning? What if you have a requirement today, would you not want to use one of the batches to cover this requirement?
If you really must not use any of the batches expiring in 6 months, why don't you just move them to blocked stock?
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dominik
We do not want to use any expired batch which is expiring during that duration.
Can we control it through MRP run that if we are running MRP for particular materials and batches of those material , which are going to expire in this duration . MRP run will not consider these batches.
BR
Ramesh Kumar