Dear SAP Experts,
we have a daily MRP run. In addition, the MRP (MD01N) run can be started manually.
In addition, we have in PPDS a MRP heuristic to delete already scheduled orders and create new orders.
When someone starts MRP live (MD01N), the orders scheduled in PPDS will be over-scheduled.
I would like to avoid that.
Is it possible to restrict the product from getting re-planned by MRP LIVE (MD01N)?
Or is it possible to start automatically the MRP heuristic after MD01N?
Perhaps there is a solution that the orders scheduled in PPDS will be not over-scheduled without fixing plan orders in PPDS.
Thanks in advance!
Kind regards,
Anne
Request clarification before answering.
Dear yasmin.alayyan,
thank you for your help. I will try it out.
Best regards,
Anne
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Anne
To avoid the rescheduling process from MRP live, you can use the fixing options to fix orders and operations.
This way the heuristic and MRP will not be able to reschedule them.
More information:
And, in case you need to change the orders again, then you can unfix them.
Best regards
Yasmin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 16 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.